Introducing last planner - Finnish experiences
Koskenvesa, A and Koskela, LJ 2005, Introducing last planner - Finnish experiences , in: 11th Joint CIB International Symposium - Combining Forces., 13– 16 June 2005, Helsinki, Finland.
| PDF - Published Version Download (134kB) |
Abstract
The Last Planner method1 represents a radically different manner of controlling production in construction. Even if its benefits are widely observed, it is also a common observation that the introduction of the Last Planner method to a site, into a company or into a country is not an easy and uncomplicated task. This paper reports on the experiences and lessons gained during the introduction of the Last Planner to Finland. A simplified explanation of Last Planner is presented. The experiences and lessons gained are contrasted with those presented in prior literature.
| Item Type: | Conference or Workshop Item (Paper) |
|---|---|
| Uncontrolled Keywords: | Last Planner System, production control, implementation |
| Themes: | Subjects / Themes > T Technology > TS Manufactures > TS155-194 Production management. Operations management Subjects outside of the University Themes |
| Schools: | Colleges and Schools > College of Science & Technology > School of the Built Environment Colleges and Schools > College of Science & Technology > School of the Built Environment > Salford Centre for Research & Innovation (SCRI) |
| Journal or Publication Title: | Proceedings of 11th Joint CIB International Symposium - Combining Forces |
| Refereed: | Yes |
| Depositing User: | LJ Koskela |
| Date Deposited: | 21 Jun 2010 11:16 |
| Last Modified: | 27 Sep 2011 12:23 |
| References: | Ballard, Glenn. 1994. The Last Planner. Northern California Construction Institute, Spring Conference, Monterey, CA, April 2224, 1994. 8 p. Ballard, Glenn. 2000. The Last Planner System of Production Control. A thesis submitted to the Faculty of Engineering of The University of Birmingham for the degree of Doctor of Philosophy. School of Civil Engineering, Faculty of Engineering, The University of Birmingham. Ballard, Glenn & Howell, Gregory. 1998. Shielding Production: Essential Step in Production Control. Journal of Construction Engineering and Management, Vol. 124, No. 1, pp. 11-17. Botero, L.F. & Álvarez, M.E. 2004. Guía de mejoramiento continuo para la productividad en la construcción de proyectos de vivienda (Lean construction como estrategia de mejoramiento). [Guide for continuous improvement for the productivity in the construction of housing projects]. REVISTA Universidad EAFIT, Vol. 40, No. 136, 2004, pp. 5084. Jaafari, Ali. 1984. Criticism of CPM for Project Planning Analysis. Journal of Construction Engineering and Management, Vol. 110, No. 2, pp. 222–233. Koskela Lauri. 2004. MakingDo – The Eighth Category of Waste. 12th Annual IGLC Conference on Lean Construction, Denmark Koskela Lauri & Howell Greg. 2002. The Theory of Project Management: Explanation to Novel Methods Proceedings of IGLC10. 10th Conference of the International Group for Lean Construction, 68 August, 2002, Gramado. Ed. by Carlos T. Formoso & Glenn Ballard. UFRGS, Porto Alegre. Pp. 1 11. Koskela, Lauri; Koskenvesa, Anssi. 2003. Last Planner –tuotannonohjaus rakennustyömaalla. [Last Planner production control on construction site]. Espoo, VTT Rakennusja yhdyskuntatekniikka, 2003. 82 p. + app. 20 p. VTT Tiedotteita Research Notes; 2197 ISBN 9513861473; 9513861481. <http://www.vtt.fi/inf/pdf/tiedotteet/2003/T2197.pdf> Koskela L, Koskenvesa A, and Sipi J. 2004. Työmaan toimiva tuotannonohjaus: Opas Last PlannerTM –menetelmaan. [Successful production control on site: Guide for the Last Planner ™ method]. Rakennusteollisuuden Kustannus, Helsinki. 42 p. |
| URI: | http://usir.salford.ac.uk/id/eprint/9380 |
Document Downloads
More statistics for this item...Actions (login required)
| Edit record (repository staff only) |

Tools
Tools